Scope
Design, construction
The Project

Project overview.

This sewage pump station was built to accommodate newly released blocks in Greenway ACT. Due to the close proximity of Lake Tuggeranong, this pump station had an off line emergency storage tank. Also in a seperate pit was a magnetic flow meter to accurately record the instantaneous flow rates as well as totalized flow from the station.

Greenway Sewage Pump Station - Switchboard
FEATURES & SPECIFICATIONS

Built to spec, built to last.

Board specifications

  • 2 x 2.4kW pumps on VSD’s
  • Allen Bradley Softstarters
  • Allen Bradley 12” HMI
  • Allen Bradley MicroLogix PLC
Project Scope

What we delivered.

Have a project like this?